Dunning Notices for 1 Dunning Run in sap fico

2 Dunning Notices for 1 Dunning Run

Question: Hi there,

There is only 1 dunning level in the dunning procedure, however, 2 dunning notice need to be generated. 1 for items overdue > 30 days, dunning notice to be sent to the customers; and 1 for items overdue > 60 days, this notice to be sent to the top management (internal) for review & decision making.

Please advice if this can be done.

Thank you!

Answer:
There is only 1 dunning level in the dunning procedure, however, 2 dunning notice need to be generated. 1 for items overdue > 30 days, dunning notice to be sent to the customers; and 1 for items overdue > 60 days, this notice to be sent to the top management (internal) for review & decision making.

Please advice if this can be done.

I would suggest to change your dunning procedure and make it 2 level. Then implement user exit via BTE 00001040 to print/e-mail/fax dunning letter from Dunning Level 1 to the Customer and e-mail internal memo from Level 2 to decision maker.