Friday, December 21, 2007

questions on account-based CO-PA

questions on account-based CO-PA

Question: 3 questions on account-based CO-PA :
1) is it possible to settle fix- and variable costs from a production order on different cost elements ?
2) is it possible to settle COGS on more than one cost element ?
3) is it possible to settle production cost variances to different cost elements ?

Thax for helping out
/Alexi

Answer:
See my reply to FICO Larry. The answer to all those questions is yes, if you have CO-PA.
_________________
ZZ

Answer:
Thanx! But in the answer "Charles" also mentioned that costing based COPA is the natural choice for this. Are you sure that account-based CO-PA supports it aswell?

In addition you wrote that one has to settle a costing run to CO-PA.
In that case I'll need to integrate CO-PC with CO-PA. But to account-based CO-PA contains only cost elements so correct me if I am wrong but
CO-PC is put into practice only with costing-based CO-PA, no!?

Answer:
Alexi,

Your assumption is correct and I apologize for not giving a complete answer before.

The "natural" choice as described by Charles is cost based CO-PA and SAP also recommends that.